| Nama Proyek | : | HIGH VOLTAGE DIRECT CURRENT (HVDC) |
| Investasi Total | : | Rp. 32,36 Triliun IDR (kurs 13000) |
| Sumber APBN-APBD | : | – |
| Sumber Swasta | : | – |
| Sumber Belum Ditentukan | : | – |
| Skema Pendanaan | : | APLN, Loan JICA |
| Lokasi | : | Sumatera Selatan, Lampung, Banten , Jawa Barat |
| Penanggung Jawab Proyek | : | PT. PLN (Persero) |
| Rencana Mulai Konstruksi | : | November 2016 |
| Rencana Mulai Operasi | : | April 2020 |
| Status Terakhir | : | 1 500 kV AC/DC Converter Stations and Substations – Pembebasan lahan – Proses Lelang Tahap 1 (Two Stage Bidding) 2 500 kV DC Submarine Cable and Switching (Connecting) Station – Ijin Penggelaran Kabel Laut telah terbit – Proses Lelang Tahap 1 (Two Stage Bidding) 3 500 kV DC Overhead Transmission Line – Pembebasan lahan – Persiapan efektif kontrak 4 AC 500 kV Overhead Transmission Line (Inc. Cilegon-Cibinong, Inc. Tasik-Depok, CS-IPP Sumsel 8) – Pembebasan lahan – Proses Evaluasi Teknis (One Stage – Two Envelopes Bidding) 5 AC 500 kV Overhead Transmission Line (CS-IPP Sumsel 9 & 10) – Menunggu kepastian lokasi IPP Sumsel 9 & 10. |
Deskripsi Proyek
HVDC adalah proyek pembangunan sistem transmisi interkoneksi anatara sumatra dan jawa , fungsinya untuk mengalirkan listrik. Proyek ini terdiri dari 5 paket proyek yang mencakup


