Name of the Project : Balikpapan-Samarinda Toll Road (99,35km)
Total Investment : Rp 9,970 Trillion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme : PRIVATE
Location : Balikpapan, East Kalimantan
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : 2017
Planned Commercial Operation Date : 2019
Latest Status : Land Procurement :
Section 1: Balikpapan KM 13 – Samboja (APBD) : 95,16%
Section 2: Samboja – Muara Jawa : 95,69%
Section 3: Muara Jawa – Palaran : 93,49%
Section 4: Palaran – Samarinda : 46,81%
Section 5: Balikpapan –Sepinggan Airport
(APBN-Loan China) : 59,09%
Construction :
Section 1: Balikpapan KM 13 – Samboja (APBD) : 53,87%
Section 2: Samboja – Muara Jawa : 0%
Section 3: Muara Jawa – Palaran : 0%
Section 4: Palaran – Samarinda : 0%
Section 5: Balikpapan –Sepinggan Airport
(APBN-Loan China) : 0,82%

Description of Project

The 99,35 km long toll road will connect two biggest cities in East Kalimantan, namely Balikpapan and Samarinda. This project is divided into two Sections, i.e., Section 1 which consists of Package 1 (25,07 km) and Package 5 (11,09 km) and Section 2 which consists of Package 2 (23,26 km), Package 3 (21,9 km) and Package 4 (17,7 km).