General Railway Organization in Jakarta

Name of the Project : General Railway Organization in Jakarta
Total Investment : Rp 7,345 Trillion
APBN-APBD Source :
Private Source :
Funding Scheme : State-Owned Enterprise
Location : Tangerang, Banten
Implementing Agency : Jakarta City Administration
Planned Construction Commencement Date : 2016
Planned Commercial Operation Date : 2019
Project Status : contruction and will be operation in 2019
Latest Status :
  • Public hearing was held on 12 May 2016 (East Jakarta) and 25 May 2016 (North Jakarta).
  • Work contract P101/corridor 1, has commenced on 22 Juni 2016 (at the Commemoration of Jakarta Anniversary) which includes preparation, green areas determination, traffic management, etc.
  • Currently, tracing process is underway. A sketch map for road axis determination to obtain approval is in the verbal process at the relevant Techincal Agencies, namely Trasportation Agency, City Planning and Jakarta City Administration

Description of Project

General Railway in the Province of Special Capital Territory of Jakarta (DKI Jakarta) will build 7 corridors of LRT Jakarta