Investment Value : IDR 5.33 Trillion
Funding Scheme : Public-Private Partnership (PPP)
Location : Banten
Project Owner : Indonesia Toll Road Authority (BPJT)
Construction Commencement Plan : 2017
Commercial Operation Date : 2019
Status Project : contruction and will be operation in 2019

Project Description

The toll road development for the length of 83.6 km to provide access to the Tanjung Lesung Special Economic Zone (SEZ) and Ujung Kulon National Park.

Project Significance

This toll road is expected to reduce logistic costs for goods delivery from the industrial estate in Pandeglang to the port in Jakarta and vice versa.

Project Development Status

CONTRUCTION STAGE

  1. The general progress of land acquisition: 22%, where the Regency / City of Serang has reached 33%
  2. KPPIP has held a coordination meeting related to the Serang Panimbang Toll Road along with the Coordinating Ministry for Political, Legal, and Security Affairs to resolve several problems in land acquisition in the field.

(Desember 2019)