Investment Value : Rp 9.9 Trillion
Funding Scheme : Public-Private Partnership (PPP)
Location : East Kalimantan
Project Owner : Indonesia Toll Road Authority (BPJT)
Construction Commencement Plan : 2017
Commercial Operation Date : 2019
Project Status : contruction and will be operation in 2019

Project Description

This 99 km toll road will connect two largest cities in East Kalimantan, namely Balikapapan and Samarinda. This project is divided into two sections, Section 1 consists of Package 1 (25.07 km) and Package 5 (11.09 km) and Section 2 consists of Package 2 (23.26 km), Package 3 (21.9 km) and Package 4 (17.7 km).

Project Significance

This toll road will support palm oil, coal, oil and gas, and agriculture-based industrial estates in the two cities and along the toll road. This toll road project will also support the projected increase of passengers and goods traffic as well as reduce logistic costs and travel time between Samarinda and Balikpapan.

Project Development Status

CONTRUCTION STAGE

  1. In general, land acquisition has reached 95.47%
  2. In general, construction progress has reached 63.47%. Section 1 has the highest construction progress, reaching 84.26%.
  3. Socialization of PerMA No. 3 2016 has been held at Balikpapan on August 30, 2018.

(Desember 2019)