Central – West Java 500 kV Transmission Line

 

Investment Value : IDR 7.64 Trillion
Funding Scheme : State-Owned Enterprice(SOE)
Location : West Java and Central Java
Project Owner : PT PLN
Target Construction Date : 2017
Commercial Operation Date : 2019
Project Status : contruction and will be operation in 2019

Project Description

The 500 kV transmission construction to transmit electricity generated in Central Java to load center Jakarta which is located in the western region of Java Island.

The transmission project is divided into the following sections:

  1. Ungaran (Pedan) – Pemalang (86 km)
  2. Pemalang – Mandirancan (167 km)
  3. Pemalang – Incomer 2 pi (110 km)
  4. Pemalang – Incomer 2 pi (Batang – Weleri) 2 km
  5. Mandirancan – Indramayu (90 km)
  6. Indramayu – Cibatu (110 km)

Project Significance

The transmission line from West Java to Central Java is highly needed to transmit the electricity generated by PLTU Indramayu (1,000 MW), PLTU Jawa 1 (1,000 MW), PLTU Pemalang (2×1,000 MW), PLTU Jawa 3 (2 x 660 MW), PLTU Jawa 4 (2×1,000 MW) and PLTU Batang (2,000 MW). Consequently, it is necessary to synchronize the development schedules and completion of all projects.