| Name of the Project | : | Sadawarna Dam |
| Total Investment | : | Rp.1,171 Trillion |
| APBN-APBD Source | : | State Budget |
| Private Source | : | – |
| Source Not Yet Determined | : | – |
| Funding Scheme | : | – |
| Location | : | Subang, West Java |
| Implementing Agency | : | Ministry of Public Works and Public Housing |
| Planned Construction Commencement Date | : | 2017 |
| Planned Commercial Operation Date | : | 2021 |
| Latest Status | : |
In the stage of land acquisition. |
Description of Project
Sadawarna Dam is located in West Java province, in the district/city of Subang. The dam is planned to have the capacity of 49M³. It is also expected to irrigate 6000 Ha land, reduce 316 M³/second and provide 0,50 M³/second.