Name of the Project : Mbay Dam
Total Investment : Rp.550 Billion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Nagekeo, East Nusa Tenggara 
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2017
Planned Commercial Operation Date : 2020
Latest Status :  Revision Process of Neighborhood Unit and Community Unit (RTRW) in  Nagekeo District to include location of the plan of Mbay Dam construction.

Description of Project

Mbay Dam is located in East Nusa Tenggara province, in the district/city of Nagekeo. The dam is planned to have the capacity of 24.91M³. It is also expected to irrigate 5206 Ha land and provide 0,54 M³/second raw water supply.