Name of the Project : Marangkayu Dam
Total Investment : 271 Billion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme : State Budget
Location : Kutai Kartanegara, East Kalimantan
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2007
Planned Commercial Operation Date : 2013
Latest Status :  

Physical Progres : 100%
On going work : preparation to clean inundated areas

Description of Project

Marangkayu dam is located in East Kalimantan province, in the district/city ofKutai Krtanegara. The dam is planned to have the capacity of 12.37M³. it is also expected to irrigate 4500 Ha land, reduce 0,75M³/second flood flow rate , provide 0,45 M³/second raw water, and generate 1,35 MW electric power.