Name of the Project : Lolak Dam
Total Investment : Rp.81 Million
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Bolaang Mongondow, North Sulawesi
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2015
Planned Commercial Operation Date : 2019
Latest Status :  

Physical Progress: 32,50%
Financial Progress 40,73%
Excavation Work in Maindam – Cofferdam, Collecting Material Work in Quarry, Stack Work in Zone 2 & 3 in maindam area, Cap. Concrete Work in the right backrest, Drilling & Grouting Maindam, Stack Work in Zone 1, 2 and 6 Cofferdam area, Dewatering Maindam and Cofferdam.

Description of Project

Lolak Dam is located in South Sulawesi province, in the district/city of Bolaang. The dam is planned to have the capacity of16.1M³. It is also expected to irrigate 3.714 Ha land, provide 0,50 M³/second raw water supply and generate 2,43 MW electrical power.