Name of the Project : Logung Dam
Total Investment : Rp.604 Billion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Kudus, Central Java
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2014
Planned Commercial Operation Date : 2018
Latest Status :  

Physical Progress: 41,03%
Finance 39,32%
Stilling Basin, Diversion Outlet and Inlet seepage, Access Road Work.

Description of Project

Logung Dam is located in Central Java province, in the district/city of Kudus. The dam is planned to have the capacity of 20.15M³. It is also expected to irrigate 282 Ha land, reduce 105 M³/second flood flow rate, provide 0,20 M³/second raw water supply and generate 0,50 MW electrical power.