Name of the Project : Cross- Border Post (PLBN) Development & Its Supporting Facilities Aruk, Sambas District, West Kalimantan
Total Investment : RP. 131.130.519.000
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme : State Budget
Location : Sambas, West Kalimantan
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 18 December 2015
Planned Commercial Operation Date : 15 December 2016
Latest Status : Financial Progress has achieved 81,08 %

Construction Progress has achieved 98 %

Description of Project

Work package of PLBN development in Aruk consists of development of Core Zone like the Main Building, Integrated Arrival Inspection Building, Clinic, Carwash Building/ disinfectant, Weighbridge Building, Truck Scanning, Integrated Departure Inspection Building, Warehouse for Confiscated Goods, Kennel, Utility Building, Check Point Building, Tasbara Monumen