Name of the Project : Construction of the new Kertajati Airport
Total Investment : Rp. 4,916 Trillion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme : Public-Private Partnership
Location : Majalengka, West Jawa
Implementing Agency : Ministry of Transportation
Planned Construction Commencement Date : 2013
Planned Commercial Operation Date : 2018
Latest Status : A. Land Acquisition Progress:
In 2016, 26,9 Ha were cleared for the runway extension that reached 3000 mThe total land that has been procured = 910 Ha + 26,9Ha + 33,1 Ha (situ eksisting has already become tha asset of the local government) = +/- 970 Ha.
B. Construction Implementation:
The construction of the land side facilities is implemented by West Government of West Java through PT.BIJB and was commenced in November 2015,
Package I: Realization of Infrastructure Work: 47,97% , data as of 2 December 2016.
Package II: Realization of the Main Passenger Terminal: 14,060% data as of 2 December 2016.
Package III: Realization of Supporting Operational Building: 10,06% data per 2 December 2016.

Description of Project

Construction of the new International Airport in Majalengka, West Java.