Name of the Project : Expansion of Ahmad Yani Airport, Semarang
Total Investment : Rp. 2 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme : State-Owned Enterprise
Location : Semarang, Central Java
Implementing Agency : PT Angkasa Pura I
Planned Construction Commencement Date : July 2017
Planned Commercial Operation Date : 2018
Latest Status : Progress of the Expansion Ahmad Yani Airport Project (PPSRG ) as of 29 May 2016 :
Package 1, progress of the 110th Week that has been aciheved:
Plan:49,559%
Realization:56,066%
Deviation: +6,507%
Package 2, progress of the 61th Week that has been aciheved:
Plan: 80,502%
Realization: 75,75%
Deviation: -4,752%
Whole progress that has been achieved :
Plan: 13,364%
Realization: 13,895%
Deviation: +0,531%

Description of Project

The details of the expansion of the 58.000 m2 Ahmad Yani Airport are as follows: capacity of passengers is 6 million per year, apron 72.522,25 m2 (wide body 2 ps and narrow body 10 ps, aviobridge 4 unit, passanger mover system, BHS, AOCC. Scope of expansion includes package 1: Infrastructure and land finalization, package 2: Apron and Exit Taxi Way, package 3 : Terminal, and package 4 : Other operational buildings.