Name of the Project | : | Construction of Sorong Seaport |
Total Investment | : | Rp 2,400 Billion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | State-Owned Enterprise |
Location | : | Sorong, West Papua |
Implementing Agency | : | PT Pelabuhan Indonesia II (Persero) |
Planned Construction Commencement Date | : | January 2018 |
Planned Commercial Operation Date | : | January 2021 |
Latest Status | : | For the latest status of the Environmental Permit (Environmenetal Impact Assessment/AMDAL), a Decision Letter on Term of Reference on Analysis of Environmetal Impact (SK ANDAL) No. SK6/PKTL.4/2/2016 has been issued. Next is the preparation of AMDAL document (Environmental Managament Plan and Environmental Monitoring Plan/RPL&RKL). |
Description of Project
Construction of Sorong Seaport project is located in West Papua province, in the district/city of Sorong. This seaport is planned to have 40 Km capacity.