Name of the Project :  Construction of Prabumulih – Kertapati railway (80km – part of Trans-Sumatera Railway)
Total Investment : Rp 1,281 Trillion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme : State Budget
Location : Prabumulih, South Sumatera
Implementing Agency : Ministry of Transportation
Planned Construction Commencement Date : March 2015
Planned Commercial Operation Date : 2019
Latest Status : The length of the railway is 80 Km’sp, along the 50 Km’sp, the railway has been installed (progress is ± 62,5%).

“Description

The construction of Prabumulih – Kertapati railway (80 km) is part of the Trans-Sumatera railway that will connect regions throughout Sumatera Island.