Name of the Project :  Construction of Jakarta-Bandung High Speed Railway 
Total Investment : Rp 66,755 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme : Private
Location :
East Jakarta, The Province of Special Capital Territory of Jakarta (DKI Jakarta)
Implementing Agency : Ministry of Transportation
Planned Construction Commencement Date : January 2017
Planned Commercial Operation Date : August 2019
Latest Status :
  1. Land acquisition has reached 82,38% or 117,23 km of 142,3 km, end of December 2016 was the last target and hopefully the whole project can be 100% completed.
  2. Road axis permit – completed.
  3. Determination of Executing Business – Completed.
  4. Permit of Railway Business – Completed.
  5. Construction Permit – Completed.
  6. Permit of ROW Toll Principle Utilization– Completed
  7.  Environmental Permit – Completed.
  8. Borrow-to-use-Permit Forest Area – Target to be Completed by December 2016.

Description of Project

Construction of Jakarta – Bandung High Speed Train railway that runs through 142,3 Km