Name of the Project : Semarang – Solo Toll Road (73km)
Total Investment : Rp 7,304 Trilion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme : Public-Private Partnership
Location : Semarang, Central Java
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : July 2009
Planned Commercial Operation Date : 2019
Latest Status : Construction
Section I (Semarang – Ungaran) 100%
Section II (Ungaran – Bawen) 100%
Section III (Bawen – Salatiga) 78,76%
Section IV (Salatiga – Boyolali) 0,00%
Section V (Boyolali – Solo) 0,00%
Land
Section I (Semarang – Ungaran) 100%
Section II (Ungaran – Bawen) 100%
Section III (Bawen – Salatiga) 95,23%
Section IV (Salatiga – Boyolali) 89,18%
Section V (Boyolali – Solo) 98,54%
Total 95,90%

 

Description of Project

The 73 km long toll road is part of the Trans Java toll road network that will reduce burden of road traffic in a connecting Solo-Ngawi road.