Name of the Project : Pematang Panggang-Kayu Agung – part of the 8 Trans Sumatera

Sections of Toll Road

Total Investment : Rp 11,646 Trillion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme : Public-Private Partnership
Location : Ogan Komering Ilir, South Sumatera
Implementing Agency : PT. Hutama Karya (Persero) Toll Road Division
Planned Construction Commencement Date : 2017
Planned Commercial Operation Date : 2020
Latest Status : Land procurement : 0%
Construction : 0%

 

Description of Project

This project is part of the Trans Sumatera Toll Road (JTTS) which will be planned to span from north to south Sumatera Island connecting Nangroe Aceh Darussalam Province and Lampung Province. This section is located in Lampung Province and South Sumatera Province with the total length of 185 km. this section is divided into three sections: (1) Section I: Terbanggi Besar – Mengala; (2) Section II: Menggala – Sp. Pematang; (3) Section III: Sp. Pematang – Kayu Agung. This section is the affiliation of Terbanggi Besar – Pematang Panggang section (100 km) and Pematang Panggang – Kayu Agung section (85 km).