Name of the Project | : | Pekanbaru – Kandis – Dumai – part of the 8 Trans Sumatera Sections of Toll Road |
Total Investment | : | Rp 16,210 Trillion |
APBN-APBD Source | : | State Budget |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | State Own Entreprise |
Location | : | Pekanbaru, Riau |
Implementing Agency | : | PT. Hutama Karya (Persero) Toll Road Division |
Planned Construction Commencement Date | : | 2016 |
Planned Commercial Operation Date | : | 2019 |
Latest Status | : | Construction Schedule : Section I July 2016-June 2018 Section II July 2016 – June 2018 Section III Jan 2017 – Dec 2018 Section IV Jan 2017 – Dec 2018 Section V June 2017-Dec 2019 Section VI June 2017-Dec 2019Progress of Land Acquisition (%) Section 1: Pekanbaru – Minas 23.28 Section 2: Minas – Petapahan 34.66 Section 3: Petapahan – North Kandis 63.10 Section 4: North Kandis– South Duri 0.00 Section 5: South Duri– North Duri 0.00 Section 6: North Duri– Dumai 6.84 TOTAL 22.71 |