Name of the Project : Palembang – Indralaya (22km) – part of the Trans Sumatera

Sections of Toll Roads

Total Investment : Rp 3.301 Trillion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme : Public-Private Partnership
Location : Palembang, South Sumatera
Implementing Agency : PT. Hutama Karya (Persero) Toll Road Division
Planned Construction Commencement Date : 2015
Planned Commercial Operation Date : 2018
Latest Status : Progress of Land Acquisition (%)
Section 1: Palembang – Pamulatan 100,00
Section 2: Pamulatan – KTM 98,63
Section 3: KTM – Simpang Indralaya 72,16
Palembang Junction 83,78
TOTAL 91,58Construction Progress (%)
Section 1: Palembang – Pamulatan : 67,77
Section 2: Pamulatan – KTM : 0,61
Section 3: KTM – Simpang Indralaya : 22,54
Palembang Junction :
TOTAL : 37,67

Description of Project

This project is part of Trans Sumatera Toll Road (JTTS) which will be planned to span from northern part to southern part of Sumatra Island connecting Nangroe Aceh Darussalam province and Lampung province. This project is one of the sections located in South Sumaterawith the total length of 22 Km and is divided into three sections: (1) Section I: Palembang – IC Pemulutan; (2) Section II: IC Pemulutan – IC KTM; (3) Section III: IC KTM – Simpang – Indralaya. This section is expected to accommodate the projection of daily traffic increase between Palembang and Indralaya cities in the Southwest of Palembang city. With the completion of the toll road, it is expected that volume of vehicles will be distributed, regional economy will be boosted and the toll road will provide access to and from Indralaya and Palembang.