| Name of the Project | : | Kertosono – Mojokerto Toll Road (41km) |
| Total Investment | : | Rp 3,480 Trillion |
| APBN-APBD Source | : | – |
| Private Source | : | – |
| Source Not Yet Determined | : | – |
| Funding Scheme | : | Private |
| Location | : | Nganjuk, East Java |
| Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
| Planned Construction Commencement Date | : | October 2012 |
| Planned Commercial Operation Date | : | 2016 |
| Latest Status | : | Construction Section I (Bandar – Jombang) 100% Section II (Jombang – Mojokerto Barat) 64,60% Section III (West Mojokerto– North Mojokerto) 100% Section IV (Bandar – West Border) 16,05% Total 78,41% Land Section I (Bandar – Jombang) 100% Section II (Jombang – west Mojokerto) 100% Section III (West Mojokerto– North Mojokerto) 100% Section IV (Bandar – West Border) 100% Total 100% |



