Name of the Project : Kertosono – Mojokerto Toll Road (41km)
Total Investment : Rp 3,480 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme : Private
Location : Nganjuk, East Java
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : October 2012
Planned Commercial Operation Date : 2016
Latest Status : Construction
Section I (Bandar – Jombang) 100%
Section II (Jombang – Mojokerto Barat) 64,60%
Section III (West Mojokerto– North Mojokerto) 100%
Section IV (Bandar – West Border) 16,05%
Total 78,41%
Land
Section I (Bandar – Jombang) 100%
Section II (Jombang – west Mojokerto) 100%
Section III (West Mojokerto– North Mojokerto) 100%
Section IV (Bandar – West Border) 100%
Total 100%

 

Description of Project

It is expected that this toll road will increase connectivity so that the economic potentials of the neighboring areas near the toll road can develop and increase efficiency of goods distribution. In the end, the toll road can boost economy and increase efficiency of goods and services. Also it can stimulate development and boost economic distribution in Java Island.