Name of the Project : Gempol – Pasuruan Toll Road (34,15km)
Total Investment : Rp 2,769 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme : Private
Location : Pasuruan, East Java
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : 2011
Planned Commercial Operation Date : 2016
Latest Status : Land Procurement :
Section 1 (Gempol-Rembang) : 98,54%
Section 2 (Rembang-Pasuruan) : 88,63% (Rembang – Kota Pasuruan) 24,32% (Kota Pasuruan) Section 3 (Pasuruan-Grati) : 4,52%
Construction :
Section 1 (Gempol-Rembang) : 96,31%
Section 2 (Rembang-Pasuruan) : 0%
Section 3 (Pasuruan-Grati) : 0%

Description of Project

Section 1 of the Gempol-Pasuruan toll road is part of the series of Gempol-Pasuruan toll road which has the length of 34,15 km spanning from Bundaran Gempol to Grati sSub District and it will connect Surabaya and Pasuruan.