Name of the Project :  
Total Investment :
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme : State Budget
Location : North Maluku
Implementing Agency : Work Unit of the Implementation of National Road for Region I North Maluku-Bina Marga, Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2016
Planned Commercial Operation Date : July 2019
Latest Status : This project consists of 10 sections, sections 1=6 have been completed, sections 7 – 10 are still in the process of construction.

Description of Project

Morotai Island Regency Administration, North Maluku, is building ring road around the island to open access of land transportation to and from Daruba City to boost tourism activities.