| Name of the Project | : | Cibitung – Cilincing Toll Road (34km) |
| Total Investment | : | Rp 4,220 Trillion |
| APBN-APBD Source | : | – |
| Private Source | : | – |
| Source Not Yet Determined | : | – |
| Funding Scheme | : | Private |
| Location | : | Bekasi, West Java |
| Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
| Planned Construction Commencement Date | : | 2017 |
| Planned Commercial Operation Date | : | 2019 |
| Latest Status | : | Land Progres • Section 1 (Cibitung – Telaga Asih), 2,96 Km : 0% • Section 2 (Telaga Asih – Tembelang), 9,41 Km : 43,42% • Section 3 (Tembelang – Mekar jaya), 13,09 Km : 11,03% • Section 4 ( Mekar jaya – Cilincing), 8,56 Km : 0% • Total : 19,92% Construction Progress No Construction Progress has been made. |