| Name of the Project | : | Ciawi – Sukabumi Toll Road (54km) |
| Total Investment | : | Rp 7,775 Trillion |
| APBN-APBD Source | : | – |
| Private Source | : | – |
| Source Not Yet Determined | : | – |
| Funding Scheme | : | Private |
| Location | : | Bogor, West Java |
| Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
| Planned Construction Commencement Date | : | 2012 |
| Planned Commercial Operation Date | : | 2017 |
| Latest Status | : | Land Procurement : Section I (Ciawi – Cigombong) : 96,45% Section II (Cigombong – Cibadak) : 0% Section III (Cibadak – West Sukabumi) : 0% Section IV (West Sukabumi– East Sukabumi) : 0% Contsruction : Section I (Ciawi – Cigombong) : 16.09% Section II (Cigombong – Cibadak) : 0% Section III (Cibadak – West Sukabumi) : 0% Section IV(West Sukabumi– East Sukabumi) : 0% |