Name of the Project : Serpong – Cinere Toll Road(10,14 km)
Total Investment : Rp 2,219 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Tangerang, Banten
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : 2017
Planned Commercial Operation Date : 2019
Latest Status : Land Progress
• Section 1 (Serpong IC – Pamulang IC), 6,675 Km : 28,95%
• Section 2 (Pamulang IC – Cinere IC), 3,647 Km : 1,66%
• Total : 21,64%
Construction Progress
No Construction progress has been made

 

Deskripsi Proyek

Serpong – Cinere Toll Road will be built for 10,14km long. This toll road will act as alternative access to Jakarta.