| Name of the Project | : | Serpong – Cinere Toll Road(10,14 km) |
| Total Investment | : | Rp 2,219 Trillion |
| APBN-APBD Source | : | – |
| Private Source | : | – |
| Source Not Yet Determined | : | – |
| Funding Scheme | : | – |
| Location | : | Tangerang, Banten |
| Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
| Planned Construction Commencement Date | : | 2017 |
| Planned Commercial Operation Date | : | 2019 |
| Latest Status | : | Land Progress • Section 1 (Serpong IC – Pamulang IC), 6,675 Km : 28,95% • Section 2 (Pamulang IC – Cinere IC), 3,647 Km : 1,66% • Total : 21,64% Construction Progress No Construction progress has been made |