Name of the Project | : | Cibitung – Cilincing Toll Road (34km) |
Total Investment | : | Rp 4,220 Trillion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | Private |
Location | : | Bekasi, West Java |
Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
Planned Construction Commencement Date | : | 2017 |
Planned Commercial Operation Date | : | 2019 |
Latest Status | : | Land Progres • Section 1 (Cibitung – Telaga Asih), 2,96 Km : 0% • Section 2 (Telaga Asih – Tembelang), 9,41 Km : 43,42% • Section 3 (Tembelang – Mekar jaya), 13,09 Km : 11,03% • Section 4 ( Mekar jaya – Cilincing), 8,56 Km : 0% • Total : 19,92% Construction Progress No Construction Progress has been made. |