Name of the Project : Cibitung – Cilincing Toll Road (34km)
Total Investment : Rp 4,220 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme : Private
Location : Bekasi, West Java
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : 2017
Planned Commercial Operation Date : 2019
Latest Status : Land Progres
• Section 1 (Cibitung – Telaga Asih), 2,96 Km : 0%
• Section 2 (Telaga Asih – Tembelang), 9,41 Km : 43,42%
• Section 3 (Tembelang – Mekar jaya), 13,09 Km : 11,03%
• Section 4 ( Mekar jaya – Cilincing), 8,56 Km : 0%
• Total : 19,92%
Construction Progress
No Construction Progress has been made.

 

Description of Project

This toll road is expected to reduce traffic load of freight transport and vehicles in Jakarta-Cikampek toll road passing through Cawang area.