Name of the Project | : | Bantaeng Industrial Zone, South Sulawesi |
Total Investment | : | Rp. |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | Private |
Location | : | Bantaeng, South Sulawesi |
Implementing Agency | : | Ministry of Industry |
Planned Construction Commencement Date | : | – |
Planned Commercial Operation Date | : | – |
Latest Status | : | Finalization of Masterplan and Startegic Plan (Renstra) for Industrial Zone in an area of 3000 ha. Ministry of Industry has formulated Detailed Spatial Planning (RDTR) in the vicinity of industrial zonePT Hwadi (China-Malaysia) and PT Bantaeng Sigma Energi are starting Construction of 2X300 MW Coal-Fired Power Plant. PT Titan and PT Hwadi have built 2 smelter plants Ministry of Industry has trained 200 Human Resources for local industry |
Description of Project
This Industrial Zone focusing on Ferronickel industry will be built on 3.000 Ha land