Name of the Project : Tukul Dam
Total Investment : 673 Billion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Pacitan, East Java
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2013
Planned Commercial Operation Date : 2017
Latest Status :  

Physical Progres: 25,63%
Finance: 22,47%
Tunnel construction, Main DAM Excavation, and Spillway.

Description of Project

Tukul Dam is located in East Java province, in the district/city of Pacitan. The dam is planned to have the capacity of 8.6843M³. It is also expected to irrigate 600 Ha land, provide 0,35 M³/second raw water supply and generate 0,64 MW electric power