Name of the Project : Tapin Dam
Total Investment : 896 Billion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Tapin, South Kalimantan
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2015
Planned Commercial Operation Date : 2019
Latest Status :  

In the process of land acquisition, of 600 Ha land, 219,88 Ha land has been realized, Withdrawal of Termin III, Preparation of First Blasting

Description of Project

Tapin Dam is located in South Kalimantan province, in the district/city of Tapin. The dam is planned to have the capacity of 56.77M³. It is also expected to irrigate 5.472 Ha land, reduce 2550 M³/second flood flow rate, provide 0,50 M³/second raw water supply and generate 3,30 MW electrical power.