Name of the Project | : | Rukoh Dam |
Total Investment | : | Rp.1,015 Trillion |
APBN-APBD Source | : | State Budget |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | – |
Location | : | Pidie, Nagroe Aceh Darussalam (NAD) |
Implementing Agency | : | Ministry of Public Works and Public Housing |
Planned Construction Commencement Date | : | 2016 |
Planned Commercial Operation Date | : | 2019 |
Latest Status | : |
Has entered the stage of the beginning of construction and is planned to be completed in 2019 |
Description of Project
Rukoh Dam is located in NAD province, in the district/city of Pidie. The dam is planned to have the capacity of 128.66M³. It is also expected to irrigate 11950 Ha land, reduce 390 M³/second flood flow rate, provide 0,85 M³/second raw water supply and generate 2,00 MW electrical power.