Name of the Project : Pidekso Dam
Total Investment : 469 Billion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Wonogiri, Central Java
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2015
Planned Commercial Operation Date : 2018
Latest Status :  

Physical Progres: 9,8%
Finance: 16,68%
On going work : Development of access road

Description of Project

Pidekso Dam is located in Central Java province, in the district/city of Wonogiri. The dam is planned to have the capacity of 21.15M³. It is also expected to irrigate 1500 Ha land and provide 0,30 M³/second raw water supply.