Name of the Project : Ladongi Dam
Total Investment : Rp.907 Billion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : East Kolaka, Southwest Sulawesi
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2016
Planned Commercial Operation Date : 2021
Latest Status :  

In the stage of Cost Estimation Planning (RPB)

Description of Project

Ladongi Dam is located in Southwest Sulawesi province, in the district/city of East Kolaka. The dam is planned to have the capacity of 25.57M³. It is also expected to irrigate 7424 Ha land, reduce 142 M³/second flood flow rate, provide 0,08M³/second raw water and generate 1,15 MW electrical power.