Name of the Project : Karalloe Dam
Total Investment : 584 Billion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Gowa, South Sulawesi
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2013
Planned Commercial Operation Date : 2017
Latest Status :  

On going works: Excavation, disposal of quarrr cover (overburden).

Description of Project