Name of the Project : Gondang Dam
Total Investment : 680 Billion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Karanganyar, Central Java
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2014
Planned Commercial Operation Date : 2018
Latest Status :  

Physical Progres: 40,50%
Finance: 37,86%
Spillway Construction has been completed Inlet Tunnel, Outlet Tunnel.

Description of Project

Gondang Dam is located in Central Java province, in the district/city of Karanganyar. The dam is planned to have the capacity of 9M³. It is also expected to irrigate 4630 Ha land and provide 0,20 M³/second raw water supply.