Name of the Project : Bendo Dam
Total Investment : 776 Billion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Ponorogo, East Java
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 2013
Planned Commercial Operation Date : 2017
Latest Status :  

Physical Progres: 29,70%
Finance: 29,70%
spillway work, inlet and outlet development, tunnel is in the process of grouting development.

Description of Project

Bendo Dam is located in East Java province, in the district/city of Ponorogo. The dam is planned to have the capacity of 43,11M³. It is also expected to irrigate 7800 Ha land and provide 0,37 M³/second raw water .