Name of the Project | : | Cross- Border Post (PLBN) Development & Its Supporting Facilities Wini, NorthTimor Tengah District, East Nusa Tenggara |
Total Investment | : | RP. 130.425.364.000 |
APBN-APBD Source | : | State Budget |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | State Budget |
Location | : | North Timor Tengah, East Nusa Tenggara |
Implementing Agency | : | Ministry of Public Works and Public Housing |
Planned Construction Commencement Date | : | 17 December 2015 |
Planned Commercial Operation Date | : | 12 December 2016 |
Latest Status | : | Financial Progress has achieved 94,12 %
Construction Progress has achieved 98,72 % |
Description of Project
Work package of PLBN development in Wini consists of the Main Building, Carwash Building, Weighbridge Scanning (x-ray) Vehicle Building, Arrival Cargo Inspection Building, warehouse of Heavy and Light Confiscated Goods, Landfil, Departure Cargo Inspection Building, Utility Building, Kennel, Check Point, Moument, Tasbara Gate and Helipad.