Name of the Project | : | Soreang – Pasirkoja Toll Road (11km) |
Total Investment | : | Rp 10,033 Trillion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | Private |
Location | : | Bandung, West Jawa |
Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
Planned Construction Commencement Date | : | 2015 |
Planned Commercial Operation Date | : | 2018 |
Latest Status | : | Land Procurement : SS Pasir Koja- SS Margaasih : 98,88% SS Margaasih- SS Katapang : 98,33% SS Katapang-BG Soreang : 97,37%Construction : SS Pasir Koja- SS Margaasih : 49,83% SS Margaasih- SS Katapang : 52,99% SS Katapang-BG Soreang : 0% |
Description of Project
This toll road connects Bandung District in Soreang area with Bandung City and is part of the effrots to reduce the current traffic problem.