Name of the Project | : | Solo – Ngawi Toll Road (90km) |
Total Investment | : | Rp 5,140 Trillion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | Public-Private Partnership |
Location | : | Solo, Central Java |
Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
Planned Construction Commencement Date | : | January 2012 |
Planned Commercial Operation Date | : | 2018 |
Latest Status | : | Construction Government Section Section I MYC 65,56% Section IA (Colomadu – Karanganyar) 87,77% Section IB (Colomadu – Karanganyar) 99,64% Colomadu – Karanganyar 100% Total 90,08% BUJT Section Section 3 (Paket 1) Solo – Mantingan 65,96% Section 4 (Paket 2) Mantingan – Ngawi 39,17% Total 52,75% Land Section 3 (Paket 1) Solo – Mantingan 91,40% Section 4 (Paket 2) Mantingan – Ngawi 91,70% Total 91,55% |