Name of the Project | : | Cileunyi – Sumedang – Dawuan Toll Road, West Java (59 km) |
Total Investment | : | Rp 10,030 Trillion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | Private |
Location | : | Bandung, West Java |
Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
Planned Construction Commencement Date | : | 2017 |
Planned Commercial Operation Date | : | 2019 |
Latest Status | : | Land Procurement : Section 1: Cileunyi – Ranca Kalong : 37,43% Section 2: Ranca Kalong – Sumedang : 93,93% Section 3: Sumedang – Cimalaka : 93,15% Section 4: Cimalaka – Legok : 1,64% Section 5: Legok – Ujung Jaya : 0% Section 6: Ujung Jaya – Dawuan : 0% Construction : Section 1: Cileunyi – Ranca Kalong : 0% Section 2: Ranca Kalong – Sumedang : 79.10% Section 3: Sumedang – Cimalaka : 0% Section 4: Cimalaka – Legok : 0% Section 5: Legok – Ujung Jaya : 0% Section 6: Ujung Jaya – Dawuan : 0% |