Name of the Project | : | Cengkareng – Batu – Ceper – Kunciran Toll Road (14,19km) |
Total Investment | : | Rp 3,507 Trillion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | Private |
Location | : | West Jakarta, The Province of Special Capital Territory of Jakarta (DKI Jakarta) |
Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
Planned Construction Commencement Date | : | 2017 |
Planned Commercial Operation Date | : | 2019 |
Latest Status | : | Land Progress • Section 1 (Kunciran – IC Sultan Ageng Tirtayasa), 2,04 Km : 7,12% • Section 2 (IC Sultan Ageng Tirtayasa – ON/Off Ramp Benteng Betawi), 3,50 Km : 0% • Section 3 (ON/Off Ramp Benteng Betawi – IC Husein Sastranegara), 6,50 Km: 18,53% • Section 4 (IC Husein Sastranegara – Benda Junction), 2,15 Km : 51,85 % • Total : 18,87% Construction Progress No Construction progress has been made |