Name of the Project :  Bogor Ring Road Toll Road (11km)
Total Investment : Rp 2,049 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme : Private
Location : Bogor, West Java
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : August 2011
Planned Commercial Operation Date : 2019
Latest Status : Land Progress

• Section 1 (Sentul Selatan – Kedung Halang), 3,85 Km : 100%
• Section 2A (Kedung Halang – Kedung Badak), 1,95 Km : 100%
• Section 2B (kedung badak – Simpang Yasmin), 2,05 km : 18,99%
• Section 3 (Simpang Yasmi – Darmaga), 3,15 Km : 0%
• Total : 88,49%
Construction Progres
• Section 1 : 100%
• Section 2A : 100%
• Section 3 : 0%
• Total : 38,67%.

Description of Project

Bogor Ring (BRR) Toll Road is expected to solve congestion in Bogor City and provide easy access for Bogor people to reach Jakarta, Soekarno-Hatta Airport, Jakarta-Cikampek Toll Road and Bandung.