Name of the Project | : | Mojokerto – Surabaya Toll Road (36km) |
Total Investment | : | Rp 3,790 Trillion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | Private |
Location | : | Mojokerto, East Java |
Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
Planned Construction Commencement Date | : | April 2012 |
Planned Commercial Operation Date | : | 2016 |
Latest Status | : | Construction Section IA 100% Section IB (Sepanjang – WRR) 75,82% Section II (WRR – Driyorejo) 13,61% Section III (Driyorejo – Krian) 33,36% Section IV (Krian – Mojokerto) 100% Total 73,57% Land Section IA 100% Section IB (Sepanjang – WRR) 95,84% Section II (WRR – Driyorejo) 89,93% Section III (Driyorejo – Krian) 84,76% Section IV (Krian – Mojokerto) 100% Total 36,47% |