Name of the Project | : | Medan- Kualanamu-Lubuk Pakam-Tebing Tinggi Toll Road (62km) |
Total Investment | : | Rp 4,072 Trillion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | Private |
Location | : | Medan, North Sumatera |
Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
Planned Construction Commencement Date | : | 2015 |
Planned Commercial Operation Date | : | 2017 |
Latest Status | : | Progress of Land Acquisition : Section I (Medan-Kualanamu), 17,8 Km : 88,90% Section II (Kualanamu-T.Tinggi), 43,9 Km : 84,27% Total : 86,37%Construction Progress: Section I & II (53,19) Section III (92,92%) Section IV (53,25%) Section V(41,33%) Section VI (41,13%) Section VII 0% Total of BUJT 42,13% Total (45,32%) |