Name of the Project : Kunciran-Serpong Toll Road(11,19km)
Total Investment : Rp 2,623 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme :
Location : Tangerang, Banten
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : 2017
Planned Commercial Operation Date : 2019
Latest Status : Land Progress
• Section 1 (South Tangerang), 9,90 Km : 26,46%
• Section 2 (Tangerang), 4,30 Km : 63,23%
• Total : 32,63%
Construction Progress
No Construction progress has been made

 

Deskripsi Proyek

Kunciran-Serpong Toll Road is part of  Jakarta Outer Ring Road (JORR) II and expected to  reduce traffic in Merak-Kebon Jeruk Toll Road andj  JORR 1.