Name of the Project | : | Depok – Antasari Toll Road (21,54km) |
Total Investment | : | Rp 2,999 Trillion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | Private |
Location | : | Depok, West Java |
Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
Planned Construction Commencement Date | : | April 2013 |
Planned Commercial Operation Date | : | 2019 |
Latest Status | : | Land Progress
• Section 1 & 2 (Antasai – Cinere), 5,80 Km : 89,50% |