Name of the Project : Cinere – Jagorawi Toll Road (14,64km)
Total Investment : Rp 2,621 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme : Private
Location : North Jakarta, The Province of Special Capital Territory of Jakarta (DKI Jakarta)
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : August 2010
Planned Commercial Operation Date : 2019
Latest Status : Land Progress

• Section 1 (Jagorawi – Raya Bogor), 3,70 Km : 94,01%
• Section 2 (Raya Bogor – Kukusan), 5,50 Km : 95,69
• Section 3 (Kukusan – Cinere), 5,44 Km : 2,79%
• Total : 63,75%
Construction Progress
• Section 1 : 100%
• Section 2A : 67,59%
• Section 2B : 45,25%
• Section 3 : 0%
• Total : 47,61%.

 

Description of Project

Cijago toll road is part of the development of the 14,64 Km Cinere-Jagorawi (Cijago) toll road.  This toll road is expected to reduce traffic congestion in Jalan Raya Bogor heading to Depok or vice versa. Section 1 ( Jagorawi – Raya Bogor ) has been in operation.