Name of the Project : Cimanggis – Cibitung Toll Road (25,39km)
Total Investment : Rp 4,525 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme : Private
Location : Depok, West Java
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : January 2013
Planned Commercial Operation Date : 2019
Latest Status : Land Progres

• Section 1 & 2 (Junction Cimanggis – Trans Yogie IC – Narogong IC), 8,75 Km : 1,64%
• Section 3 & 4 (Narogong IC – Setu – Cibitung Junction), 16,46 Km : 0,85%
• Total : 1,20%
Construction Progress
• Section 1 : 20,35%
• Total : 4,26%.

 

Description of Project

Cimanggis – Cibitung Toll Road is part of Jakarta Outer Ring Road (JORR) II built with the purpose to reduce traffic load at routes passing through Jakarta.